United Arab Emirates, Oil & Gas Onshore

Project: Upgrade & Modification works for Pipeline & Terminals
Owner: ADNOC Onshore
Client: Control Contracting & Trading Company (CCTC)
Executing Company: KAEFER LLC
Services Executed: Passive Fire Protection, Painting, Scaffolding
Man-hours: 190,381
Time frame: 2019 - 2021

Passive Fire Protection - Fendolite (33.5 mm): 14,203 m²
Passive Fire Protection - intumescent (12.2 mm): 1,993 m²
Structural Painting (for intumescent): 1,993 m²
Structural Painting (for cementitious): 14,203 m³