Project: Eskom Power Station Tutuka
Owner: Eskom
Executing Company: KAEFER Thermal Contracting Services (PTY) LTD.
Services Executed: Scaffolding, Removal of Insulation
Man-hours without LTI: 5,517,976*
Time frame: 2020 - 2021

Tutuka is the Zulu word for progress. Since its completion in 1996, the Tutuka power station is feeding energy into Eskom's 765kV extra high voltage system. The six boiler/turbine unit giant contributes 3,600MW supplied to consumers and industries throughout the country. KAEFER in South Africa is delivering supply, erection & dismantling of scaffolding including removal & replacement of insulation materials based on defects and scopes provided by Eskom within its maintenance and outage contract.

*total hours until 2020